Petroleum Exploration v. Hensley
213 S.W.2d 262
Aug. 6, 1948.
ACTION: Judgment reversed with directions.


Appeal from Circuit Court, Clay County; Ray Lewis, Judge.
Action by Petroleum Exploration, a corporation, against William Henry Hensley and others, to condemn an easement over and through the land of defendants for purpose of laying a pipe line to be used to transmit gas for public use. From an adverse judgment, plaintiff appeals.

LATIMER, Justice.
This action was instituted by appellant, Petroleum Exploration, a corporation, as plaintiff below to condemn an easement over and through the land of appellees for the purpose of laying a pipeline to be used to transmit gas for public use.

Appellant owns and operates gas wells near Oneida in Clay County; and owns and operates transmission lines running from there to Lexington and Somerset, through which it distributes gas for public use at Lexington, Richmond, Irvine, Manchester, London and Somerset. Appellant owns and operates a number of gas wells in Knox County and is now in the process of further development there. For the purpose of providing more gas and also to overcome the gas shortages which have occurred during the winters past, it is now constructing about 34 miles of new pipeline from the Knox County field to the Clay County terminus near Oneida. Appellant selected and proposed what it deemed the most feasible and practicable route for the construction of this line through the intervening mountainous country. The route as proposed and selected traverses the land of appellee, William Henry Hensley, for a distance of about 882 feet and passes through a small bottom which is bounded on the West by Goose Creek and on the East by a hillside and high steep cliff. Between the defendants' land and the abrupt cliff on the East is a hillside, composed of rocks, boulders, and earth, rising at an angle of about 45 degrees with a series of irregular benches or ledges on the face of the cliff. Both the hillside and the cliff are owned by the Hardwood Sales Company. Efforts were made to agree with appellees, Mr. and Mrs. Hensley, for the right-of-way over this land. The Hensleys demanded either free gas indefinitely or an annual money rental of $25 per year for the right to traverse their land. This appellant thought to be a prohibitive annual carrying charge. After having exhausted every effort to agree, this action was instituted.

Commissioners were appointed who went upon the land and assessed the damages at $175. Appellees, as defendants below, filed their exceptions which challenged the necessity for taking an easement in the land and also the amount of the award.

The County Court then without the intervention of jury tried the issue of necessity and after viewing the property, held it was not necessary for plaintiff to cross the defendant's property, and dismissed the petition. The matter of necessity and affirmed the County Court's ruling. From that judgment this appeal is prosecuted.

Appellees take the position that appellant can and should construct its pipeline on the hillside rather than through this bottom land. The only testimony introduced was that of Paul E. Landrus, Superintendent of gas production and transportation of pipeline for the Petroleum Exploration, who testified for appellant, and that of William Hensley, who testified for himself. Mr. Hensley, according to his testimony, is without training or experience either as an engineer or in locating and laying of pipelines. He insisted that it would be feasible and practicable for appellant to lay its line along the ledges on the hillside although it might be a bit more inconvenient so to do. He insists it is not at all necessary to go through his land and that the only reason for so doing is that it should be easier and more convenient.

According to the testimony of appellant, in laying lines it is necessary to stay either on top of the ridges or in the bottoms as much as possible and in going from one to the other it is necessary to go straight up or down the hill as perpendicularly as possible; and that if a line is built along the hillside the hazards of slips and slides are incurred, which frequently result in a breaking of the line with consequent dangers.

Appellees quite frankly admit that the construction of gas pipelines in themselves is a necessity in order to serve the public with this service, and that because thereof the Legislature grants general condemnation rights for the benefit of the public.

But, it is insisted that the question of necessity as to a particular location, or property, that is, whose land such pipelines shall cross or go over and through, lies clearly within the purview of the court, and is a matter entirely for judicial determination. Appellees admit that the rule of absolute necessity cannot be set up and relied upon but insist that it is neither a matter of convenience. There must appear a reasonable necessity therefor.

Appellant quite as frankly admits that it would be physically possible as an engineering feat to construct a pipeline anywhere, but insist that the rule of 'mere physical possibility' would be putting it in the category of absolute necessity. Certainly appellant cannot capriciously or wantonly locate its line so as to injure appellees, nor would it be enough for appellant to say that as a mere convenience it desires to go through the land of appellees. The question is: In the light of the facts here, is the course as desired a practical necessity? The evidence shows that it is not practicable to lay a gas line alongside a hill because of the danger of slips and slides, with their accompanying hazards. Common judgment supports this.

We have here the admitted public necessity for the pipeline. Appellant has no property of its own through which it may lay its pipeline. Consequently, the pipeline must be laid through the property of someone.

We are convinced that, under the facts above and the rule of law applicable as laid down by this Court relative to necessity, there exists here a practicable and reasonable necessity for an easement through the land of appellees.

Wherefore, the judgment is reversed with directions for further proceedings in the Clay Circuit Court by the General Assembly at its regular session in 1948.

Ky.,1948
PETROLEUM EXPLORATION v. HENSLEY
213 S.W.2d 262, 308 Ky. 103


     